Everything you need to know about net metering concept in India

Vishal Phadke    Aug 30th, 2020   |   Sunday

When one considers all the different sources of renewable energy, solar is coming up to be the most viable and sustainable source, both at institutional as well as at individual levels. A simple rooftop could be converted into a solar power plant. It is that easy!

These days, not only can you generate and use the energy, you could also transfer the excess production to the grid and earn credit, something in industrial terms called “net metering” .

Net metering:The concept

Net metering is an electricity policy for utility customers who operate their own on-site self-generation solar power systems. It allows consumers to feed surplus solar power into the grid when they don’t need it, and receive a credit on their electricity bill. This takes care of the problem of matching power supply and demand, which will never match perfectly for any building. Net metering effectively uses the grid as a huge battery, which helps to balance this demand/supply mismatch.

Without solar net metering , many rooftop solar plants – and residential ones in particular – would require a battery backup to even out the power consumption through the day. Battery costs have been falling rapidly, and will become an important part of the solar industry someday – but today, very few solar plants would be financially attractive once battery costs are built in. Although, the concept of net metering first emerged in United States in 1979 as a way to compensate customers for their investment in renewable energy , it makes much more sense than just being a financial implication.

How it works

The solar power systems are connected to the utility grid via the customers’ main service panel and meter and, when generating more power than is needed at the site, return excess electricity to the grid through the power meter, reversing the meter from its usual direction. Thus, a bi-directional meter is needed to avail net metering. Since the meter works in both directions (i.e. bi-directional meter)– one way to measure power purchased (when on-site demand is greater than on-site power production), and the other way to measure power returned to the grid – the customer pays the “net” of both transactions.

It changes the game

The solar net metering policy makes solar energy more attractive and affordable for users. It can help users save a huge amount of money, and it makes the process of accounting for the energy flowing to and from the utility simpler and easier to administer.
For example, if you live in a state which has implemented the solar net metering policy, then you get credited for the electricity you deliver back to the grid at the same retail price that you pay for the electricity you take from the grid. The banking happens for a period of time, usually annually. This not only brings down the energy cost drastically, but helps create small power generation units in almost every nook and corner of the country.

Net Metering: The challenges

With fundamental economics getting stronger, solar doesn’t require subsidies so much as enabling policies like net metering.

Many states in India have now created net metering policies, although implementation has been slow in most cases, and in others there are arbitrary constraints and limits. For example, net metering in Tamil Nadu is not allowed for high-tension consumers, which are the largest consumers. In many states, there is a cap on the size of the project which can avail net metering, which prevents large customers from fully using their rooftops.
For example, in Maharshtra, there is an artificial capacity constraint of 1 MWp. This means that even if the consumer has the space to accommodate more than 1 MWp system, net metering policy would allow only 1 MWp system to be installed under its scheme.

“Rooftop solar sector has not really taken off mainly due to the poor implementation of net metering policy,” Kuldeep Jain, Managing Director, CleanMax recently stated in The Hindu. He further suggested that the net metering policies in most states are not being implemented. There is a lack of follow-through. For example, in Maharashtra, no forms have been released and no processes have been put in place on how to implement net metering.

The below tabs gives you and easy to use reference of the different Net Metering policies across Indian states and the different approvals, charges applicable across states.


States Year of release of Net Metering policies Gross / Net Metering Specifications on capacity Specifications for grid integration (electricity or power)
Range allowed Max. capacity w.r.t sanctioned load Limitations on transformer capacity Export of electricity allowed when compared to consumption Billing period for settlement Compensation period for surplus
Maharashtra 2015 Net 1 kW–1 MW 100% 40% Above 100% Monthly Yearly
Uttar Pradesh* 2019 Both 1 kW–2 MW 100% 25% Above 100% Monthly Yearly
Rajasthan 2015 Net 1 kW–1 MW 80% 30% Above 100% Monthly Yearly
Karnataka 2016 Both 1 kW–1 MW 100% 80% Above 100% Monthly Monthly
Haryana 2014 Both 1 kW–1 MW 100% 30 % for LT and 15% for HT 90% Monthly Yearly
Tamil Nadu 2019 Net Consumers under Low Tension category except Hut and Agricultural category of tariff – Not sure 100% 90% 90% Bi-monthly Yearly
Delhi 2014 Net 1 kW – NA; for group / virtual metering 5 kW – 5 MW 100% 20% Above 100% Monthly Yearly
Telangana 2016 Both 1 kW–1 MW Residential: 100% Others: 80% 80% Above 100% Monthly Half-yearly
Gujarat 2016 Both 1 kW–1 MW Residential- Above 100%; Non- residential 50 % (for initial two years) 65% Above 100% Monthly Yearly
Andhra Pradesh 2015 Both 1 kW–1 MW 100% 80 % Above 100% Monthly Quarterly
West Bengal 2013 Net 5 kW–not specified NA NA 90% Monthly Yearly
UTs – Andaman & Nicobar, Chandigarh, Dadar and Nagar Haveli, Daman & Diu, Lakshadweep, Puducherry 2019 Both NA–500 kWp; for group/ virtual net metering 5 kWp–NA 100% 75% Above 100% Monthly Yearly
Madhya Pradesh 2015 Net NA–1 MW 100% 30%, as per amendment in 2017 Above 100% Monthly Yearly
Punjab 2015 Net 1 kW–1 MW 80% 30% 90% Monthly Yearly
Jammu and Kashmir 2015 Net 1 kW–1 MW 50% 20% 90% Monthly Yearly
Orissa Amended in 2018 Net Up to sanctioned load 100% 75% 90% Monthly Yearly
Kerala 2014 Net 1 kW–1 MW NA 80% Above 100% Monthly Yearly
Assam 2015 Both 1kW–1 MW 80% 20% 90% Monthly Yearly
Jharkhand 2015 Both 1 kW–2 MW 100% 100% Above 100% Monthly Yearly

Year of release of Net Metering policies

2015

Gross / Net Metering

Net

Specifications on capacity

Range allowed

1 kW–1 MW

Max. capacity w.r.t sanctioned load

100%

Limitations on transformer capacity

40%

Specifications for grid integration (electricity or power)

Export of electricity allowed when compared to consumption

Above 100%

Billing period for settlement

Monthly

Compensation period for surplus

Yearly

Year of release of Net Metering policies

2019

Gross / Net Metering

Both

Specifications on capacity

Range allowed

1 kW–2 MW

Max. capacity w.r.t sanctioned load

100%

Limitations on transformer capacity

25%

Specifications for grid integration (electricity or power)

Export of electricity allowed when compared to consumption

Above 100%

Billing period for settlement

Monthly

Compensation period for surplus

Yearly

Year of release of Net Metering policies

2015

Gross / Net Metering

Net

Specifications on capacity

Range allowed

1 kW–1 MW

Max. capacity w.r.t sanctioned load

80%

Limitations on transformer capacity

30%

Specifications for grid integration (electricity or power)

Export of electricity allowed when compared to consumption

Above 100%

Billing period for settlement

Monthly

Compensation period for surplus

Yearly

Year of release of Net Metering policies

2016

Gross / Net Metering

Both

Specifications on capacity

Range allowed

1 kW–1 MW

Max. capacity w.r.t sanctioned load

100%

Limitations on transformer capacity

80%

Specifications for grid integration (electricity or power)

Export of electricity allowed when compared to consumption

Above 100%

Billing period for settlement

Monthly

Compensation period for surplus

Monthly

Year of release of Net Metering policies

2014

Gross / Net Metering

Both

Specifications on capacity

Range allowed

1 kW–1 MW

Max. capacity w.r.t sanctioned load

100%

Limitations on transformer capacity

30% for LT and 15% for HT

Specifications for grid integration (electricity or power)

Export of electricity allowed when compared to consumption

90%

Billing period for settlement

Monthly

Compensation period for surplus

Yearly

Year of release of Net Metering policies

2019

Gross / Net Metering

Net

Specifications on capacity

Range allowed

Consumers under Low Tension category except Hut and Agricultural category of tariff – Not sure

Max. capacity w.r.t sanctioned load

100%

Limitations on transformer capacity

90%

Specifications for grid integration (electricity or power)

Export of electricity allowed when compared to consumption

90%

Billing period for settlement

Bi-monthly

Compensation period for surplus

Yearly

Year of release of Net Metering policies

2014

Gross / Net Metering

Net

Specifications on capacity

Range allowed

1 kW – NA; for group / virtual metering 5 kW – 5 MW

Max. capacity w.r.t sanctioned load

100%

Limitations on transformer capacity

20%

Specifications for grid integration (electricity or power)

Export of electricity allowed when compared to consumption

Above 100%

Billing period for settlement

Monthly

Compensation period for surplus

Yearly

Year of release of Net Metering policies

2016

Gross / Net Metering

Both

Specifications on capacity

Range allowed

1 kW–1 MW

Max. capacity w.r.t sanctioned load

Residential: 100% Others: 80%

Limitations on transformer capacity

80%

Specifications for grid integration (electricity or power)

Export of electricity allowed when compared to consumption

Above 100%

Billing period for settlement

Monthly

Compensation period for surplus

Half-yearly

Year of release of Net Metering policies

2016

Gross / Net Metering

Both

Specifications on capacity

Range allowed

1 kW–1 MW

Max. capacity w.r.t sanctioned load

Residential- Above 100%; Non- residential 50 % (for initial two years)

Limitations on transformer capacity

65%

Specifications for grid integration (electricity or power)

Export of electricity allowed when compared to consumption

Above 100%

Billing period for settlement

Monthly

Compensation period for surplus

Yearly

Year of release of Net Metering policies

2015

Gross / Net Metering

Both

Specifications on capacity

Range allowed

1 kW–1 MW

Max. capacity w.r.t sanctioned load

100%

Limitations on transformer capacity

80 %

Specifications for grid integration (electricity or power)

Export of electricity allowed when compared to consumption

Above 100%

Billing period for settlement

Monthly

Compensation period for surplus

Quarterly

Year of release of Net Metering policies

2013

Gross / Net Metering

Net

Specifications on capacity

Range allowed

5 kW–not specified

Max. capacity w.r.t sanctioned load

NA

Limitations on transformer capacity

NA

Specifications for grid integration (electricity or power)

Export of electricity allowed when compared to consumption

90%

Billing period for settlement

Monthly

Compensation period for surplus

Yearly

Year of release of Net Metering policies

2019

Gross / Net Metering

Both

Specifications on capacity

Range allowed

NA–500 kWp; for group/ virtual net metering 5 kWp–NA

Max. capacity w.r.t sanctioned load

100%

Limitations on transformer capacity

75%

Specifications for grid integration (electricity or power)

Export of electricity allowed when compared to consumption

Above 100%

Billing period for settlement

Monthly

Compensation period for surplus

Yearly

Year of release of Net Metering policies

2015

Gross / Net Metering

Net

Specifications on capacity

Range allowed

NA–1 MW

Max. capacity w.r.t sanctioned load

100%

Limitations on transformer capacity

30%, as per amendment in 2017

Specifications for grid integration (electricity or power)

Export of electricity allowed when compared to consumption

Above 100%

Billing period for settlement

Monthly

Compensation period for surplus

Yearly

Year of release of Net Metering policies

2015

Gross / Net Metering

Net

Specifications on capacity

Range allowed

1 kW–1 MW

Max. capacity w.r.t sanctioned load

80%

Limitations on transformer capacity

30%

Specifications for grid integration (electricity or power)

Export of electricity allowed when compared to consumption

90%

Billing period for settlement

Monthly

Compensation period for surplus

Yearly

Year of release of Net Metering policies

2015

Gross / Net Metering

Net

Specifications on capacity

Range allowed

1 kW–1 MW

Max. capacity w.r.t sanctioned load

50%

Limitations on transformer capacity

20%

Specifications for grid integration (electricity or power)

Export of electricity allowed when compared to consumption

90%

Billing period for settlement

Monthly

Compensation period for surplus

Yearly

Year of release of Net Metering policies

Amended in 2018

Gross / Net Metering

Net

Specifications on capacity

Range allowed

Up to sanctioned load

Max. capacity w.r.t sanctioned load

100%

Limitations on transformer capacity

75%

Specifications for grid integration (electricity or power)

Export of electricity allowed when compared to consumption

90%

Billing period for settlement

Monthly

Compensation period for surplus

Yearly

Year of release of Net Metering policies

2014

Gross / Net Metering

Net

Specifications on capacity

Range allowed

1 kW–1 MW

Max. capacity w.r.t sanctioned load

NA

Limitations on transformer capacity

80%

Specifications for grid integration (electricity or power)

Export of electricity allowed when compared to consumption

Above 100%

Billing period for settlement

Monthly

Compensation period for surplus

Yearly

Year of release of Net Metering policies

2015

Gross / Net Metering

Both

Specifications on capacity

Range allowed

1 kW–1 MW

Max. capacity w.r.t sanctioned load

80%

Limitations on transformer capacity

20%

Specifications for grid integration (electricity or power)

Export of electricity allowed when compared to consumption

90%

Billing period for settlement

Monthly

Compensation period for surplus

Yearly

Year of release of Net Metering policies

2015

Gross / Net Metering

Both

Specifications on capacity

Range allowed

1kw –3 MW

Max. capacity w.r.t sanctioned load

100%

Limitations on transformer capacity

100%

Specifications for grid integration (electricity or power)

Export of electricity allowed when compared to consumption

Above 100%

Billing period for settlement

Monthly

Compensation period for surplus

Yearly



* The applicable rate will be 30 % of the weighted APPC rate at which the DISCOM has purchased power from the ground mounted solar PV plant up to 5 MW capacity

Source: Centre for Energy Finance, Individual DISCOM websites

Disclaimer: The information presented above is for educational purposes only. All the data provided in the table above are approximate values derived from third party sources, research articles or on ground experience and CleanMax would take no responsibility or have any obligation over the correctness of data. The regulatory policies get updated from time to time and it is highly encouraged that you head over to individual DISCOM sites to refer the latest changes.


Acronyms Used:

APPC Average Power Purchase Cost
State Pages on Website Eligibility Criteria for Net Metering i.e. Upper cap and Lower cap Banking Norms for Rooftop Key Approvals required for Rooftop DISCOMs   Key Regulatory Charges/exemptions for Rooftop (if any) For more details visit individual DISCOM website.
Maharashtra 1 kW–1 MW Yearly 1. CEIG approval
2. The consumer and the DISCOM will enter into a Net Metering Connection Agreement, which shall remain in force for 20 years, in the prescribed format after the roof-top solar PV system is installed but before it is synchronized with the distribution network
The rooftop solar system installed on eligible consumer premises, are exempt from payment of banking and wheeling charges and losses, cross subsidy and additional surcharge etc. Project wise Statutory fees, testing fees, supervision charges, application fees etc. are applicable and varies time to time as policy changes
Uttar Pradesh 1 kW–2 MW Yearly 1. CEIG approval
2. No net metering
Rooftop solar PV system under gross metering scheme / net metering scheme, whether self-owned or third party owned and installed on eligible consumer premises are exempt from payment of wheeling and cross subsidy surcharge.
Rajasthan 1 kW–1 MW Yearly 1. CEIG approval
2. Any eligible consumer under the Rajasthan Net Metering Regulations may obtain approval for installation of rooftop solar system on its premises under net metering arrangement in accordance with the Rajasthan Net Metering Regulations and execution of an interconnection agreement for net metering with the distribution licensee.
Rooftop PV solar power plants under net metering arrangement are exempt from payment of wheeling, banking and cross subsidy surcharges.
Karnataka 1 kW–1 MW Monthly 1. CEIG approval (Applicable above 1MW)
2. Net metering approval (if applicable up to 1 MW)
Transmission and wheeling charges will not be applicable to rooftop solar projects to the extent there is no wheeling of such electricity. In case it is a ground mount project then banking and wheeling charges may be applicable
Haryana NA–1 MW Yearly 1. CEIG approval
2. Net metering approval (if applicable) or a ‘no-objection certificate’ from the applicable local distribution utility. The consumer and the distribution utility will enter into a Net Metering Connection Agreement in the prescribed format after the roof-top solar PV system is installed but before it is synchronized with the distribution network.
While the Haryana Solar Policy has waived electricity taxes, electricity cess, electricity duty, and cross subsidy charges etc., but Transmission, wheeling and banking charges may be applicable as per the guidelines and orders issued by the HERC from time to time.
Tamil Nadu Consumers under Low Tension category except Hut and Agricultural category of tariff Yearly

1. CEIG approval
2. Net metering approval (if applicable) or NOC from Tangedco
3. Ministry clearance
4. Reverse test report (RTR) from local Tangedco

Transmission and wheeling charges will not be applicable to rooftop solar projects to the extent there is no wheeling of such electricity.
Delhi 1 kW – NA* Yearly 1. CEIG approval
2. Net metering approval (if applicable) or NOC from DISCOM
In order to promote the third party owned systems and avoid complexities around evaluation and monitoring of wheeling/banking/open access charges, the net metering rooftop solar arrangements are specifically exempted from these charges
Telangana 1 kW–1 MW Half-yearly 1. CEIG Approval
2. The Net metering connection agreement has to be executed by the Consumer with the DISCOM within 15 days of receipt of the technical feasibility approval
3. On inspection of the equipment SPV system are to be synchronized within 10 working days, provided the systems are installed as per the norms and standards
1. Tariff payable by the DISCOM is the APCC of the DISCOM
2. Exempted from transmission charges, transmission loss, wheeling charge, wheeling loss, cross subsidy surcharge and additional surcharge
3. The CDM benefits shall be retained by the consumer for the first year and second year onwards, 10%, progressively increasing by 10% each year till the benefits are shared in equal proportion
Gujarat 1 kW–1 MW Yearly 1. CEIG approval
2. Net metering approval (OPEX project not allowed under net metering regulation. Only CAPEX projects considered for net metering) or NOC from DISCOM
Project wise Statutory fees, testing fees, supervision charges, application fees etc. are applicable and varies time to time as policy changes
Andhra Pradesh 1 kW–1 MW Quarterly 1. CEIG approval
2. Net metering approval (if applicable) or NOC from DISCOM
No Distribution losses and charges will be collected from the Eligible Developers /Group /Society /Individuals by the DISCOMs. All other charges shall be applicable as per the Tariff Order amended from time to time.
West Bengal 5 kW–not specified Yearly 1. CEIG approval
2. Net metering approval (if applicable) or NOC from DISCOM
Transmission and wheeling charges will not be applicable to rooftop solar projects to the extent there is no wheeling of such electricity.
Puducherry NA–500 kWp; Yearly 1. CEA (Central electrical authority) approval
2. Net metering approval (if applicable)
Transmission and wheeling charges will not be applicable to rooftop solar projects to the extent there is no wheeling of such electricity

Eligibility Criteria for Net Metering i.e. Upper cap and Lower cap

1 kW–1 MW

Banking Norms for Rooftop

Yearly

Key Approvals required for Rooftop

  1. CEIG approval
  2. The consumer and the DISCOM will enter into a Net Metering Connection Agreement, which shall remain in force for 20 years, in the prescribed format after the roof-top solar PV system is installed but before it is synchronized with the distribution network

Key Regulatory Charges/exemptions for Rooftop (if any) For more details visit individual DISCOM website.

The rooftop solar system installed on eligible consumer premises, are exempt from payment of banking and wheeling charges and losses, cross subsidy and additional surcharge etc. Project wise Statutory fees, testing fees, supervision charges, application fees etc. are applicable and varies time to time as policy changes

Eligibility Criteria for Net Metering i.e. Upper cap and Lower cap

1 kW–2 MW

Banking Norms for Rooftop

Yearly

Key Approvals required for Rooftop

  1. CEIG approval
  2. No net metering

Key Regulatory Charges/exemptions for Rooftop (if any) For more details visit individual DISCOM website.

Rooftop solar PV system under gross metering scheme / net metering scheme, whether self-owned or third party owned and installed on eligible consumer premises are exempt from payment of wheeling and cross subsidy surcharge.

Eligibility Criteria for Net Metering i.e. Upper cap and Lower cap

1 kW–1 MW

Banking Norms for Rooftop

Yearly

Key Approvals required for Rooftop

  1. CEIG approval
  2. Any eligible consumer under the Rajasthan Net Metering Regulations may obtain approval for installation of rooftop solar system on its premises under net metering arrangement in accordance with the Rajasthan Net Metering Regulations and execution of an interconnection agreement for net metering with the distribution licensee.

Key Regulatory Charges/exemptions for Rooftop (if any) For more details visit individual DISCOM website.

Rooftop PV solar power plants under net metering arrangement are exempt from payment of wheeling, banking and cross subsidy surcharges.

Eligibility Criteria for Net Metering i.e. Upper cap and Lower cap

1 kW–1 MW

Banking Norms for Rooftop

Yearly

Key Approvals required for Rooftop

  1. CEIG approval (Applicable above 1MW)
  2. Net metering approval (if applicable up to 1 MW)

Key Regulatory Charges/exemptions for Rooftop (if any) For more details visit individual DISCOM website.

Transmission and wheeling charges will not be applicable to rooftop solar projects to the extent there is no wheeling of such electricity. In case it is a ground mount project then banking and wheeling charges may be applicable

Eligibility Criteria for Net Metering i.e. Upper cap and Lower cap

NA–1 MW

Banking Norms for Rooftop

Yearly

Key Approvals required for Rooftop

  1. CEIG approval
  2. Net metering approval (if applicable) or a ‘no-objection certificate’ from the applicable local distribution utility.The consumer and the distribution utility will enter into a Net Metering Connection Agreement in the prescribed format after the roof-top solar PV system is installed but before it is synchronized with the distribution network.

Key Regulatory Charges/exemptions for Rooftop (if any) For more details visit individual DISCOM website.

While the Haryana Solar Policy has waived electricity taxes, electricity cess, electricity duty, and cross subsidy charges etc., but Transmission, wheeling and banking charges may be applicable as per the guidelines and orders issued by the HERC from time to time.

Eligibility Criteria for Net Metering i.e. Upper cap and Lower cap

Consumers under Low Tension category except Hut and Agricultural category of tariff

Banking Norms for Rooftop

Yearly

Key Approvals required for Rooftop

  1. CEIG approval
  2. Net metering approval (if applicable) or NOC from Tangedco
  3. Ministry clearance
  4. Reverse test report (RTR) from local Tangedco

Key Regulatory Charges/exemptions for Rooftop (if any) For more details visit individual DISCOM website.

Transmission and wheeling charges will not be applicable to rooftop solar projects to the extent there is no wheeling of such electricity.

Eligibility Criteria for Net Metering i.e. Upper cap and Lower cap

1 kW – NA*

Banking Norms for Rooftop

Yearly

Key Approvals required for Rooftop

  1. CEIG approval
  2. Net metering approval (if applicable) or NOC from DISCOM

Key Regulatory Charges/exemptions for Rooftop (if any) For more details visit individual DISCOM website.

In order to promote the third party owned systems and avoid complexities around evaluation and monitoring of wheeling/banking/open access charges, the net metering rooftop solar arrangements are specifically exempted from these charges

Eligibility Criteria for Net Metering i.e. Upper cap and Lower cap

1 kW–1 MW

Banking Norms for Rooftop

Half-yearly

Key Approvals required for Rooftop

  1. CEIG approval
  2. The Net metering connection agreement has to be executed by the Consumer with the DISCOM within 15 days of receipt of the technical feasibility approval
  3. On inspection of the equipment SPV system are to be synchronized within 10 working days, provided the systems are installed as per the norms and standards

Key Regulatory Charges/exemptions for Rooftop (if any) For more details visit individual DISCOM website.

  1. Tariff payable by the DISCOM is the APCC of the DISCOM
  2. Exempted from transmission charges, transmission loss, wheeling charge, wheeling loss, cross subsidy surcharge and additional surcharge
  3. The CDM benefits shall be retained by the consumer for the first year and second year onwards, 10%, progressively increasing by 10% each year till the benefits are shared in equal proportion

Eligibility Criteria for Net Metering i.e. Upper cap and Lower cap

1 kW–1 MW

Banking Norms for Rooftop

Yearly

Key Approvals required for Rooftop

  1. CEIG approval
  2. Net metering approval (OPEX project not allowed under net metering regulation. Only CAPEX projects considered for net metering) or NOC from DISCOM

Key Regulatory Charges/exemptions for Rooftop (if any) For more details visit individual DISCOM website.

Project wise Statutory fees, testing fees, supervision charges, application fees etc. are applicable and varies time to time as policy changes

Eligibility Criteria for Net Metering i.e. Upper cap and Lower cap

1 kW–1 MW

Banking Norms for Rooftop

Quarterly

Key Approvals required for Rooftop

  1. CEIG approval
  2. Net metering approval (if applicable) or NOC from DISCOM

Key Regulatory Charges/exemptions for Rooftop (if any) For more details visit individual DISCOM website.

No Distribution losses and charges will be collected from the Eligible Developers /Group /Society /Individuals by the DISCOMs. All other charges shall be applicable as per the Tariff Order amended from time to time.

Eligibility Criteria for Net Metering i.e. Upper cap and Lower cap

5 kW–not specified

Banking Norms for Rooftop

Yearly

Key Approvals required for Rooftop

  1. CEIG approval
  2. Net metering approval (if applicable) or NOC from DISCOM

Key Regulatory Charges/exemptions for Rooftop (if any) For more details visit individual DISCOM website.

Transmission and wheeling charges will not be applicable to rooftop solar projects to the extent there is no wheeling of such electricity.

Eligibility Criteria for Net Metering i.e. Upper cap and Lower cap

NA–500 kWp;

Banking Norms for Rooftop

Yearly

Key Approvals required for Rooftop

  1. CEA (Central electrical authority) approval
  2. Net metering approval (if applicable)

Key Regulatory Charges/exemptions for Rooftop (if any) For more details visit individual DISCOM website.

Transmission and wheeling charges will not be applicable to rooftop solar projects to the extent there is no wheeling of such electricity



* Subject to
- feasibility of interconnection with grid
- available capacity of service line connection of consumer of premise
- the sanctioned load of consumer of the premise

Source: Centre for Energy Finance, Individual DISCOM websites

Disclaimer: The information presented above is for educational purposes only. All the data provided in the article above are approximate values derived from third party sources, research articles or on ground experience and CleanMax would take no responsibility or have any obligation over the correctness of data. The regulatory policies get updated from time to time and it is highly encouraged that you head over to individual DISCOM sites to refer the latest changes.


Acronyms Used:

NOC No Objection Certificate
HERC Haryana Electricity Regulatory Commission
APPC Average Power Purchase Cost
CEIG Chief Electrical Inspector to Government
CDM Clean Development Mechanism


The way ahead

Agreed, a greener and cleaner environment is the biggest benefit one could have because of solar energy adoption but complimenting it with additional monetary benefit always helps. As the union government is extending all help to expand the solar base, it must come up with better ways to implement the policy framework on net metering in India so that the ambitious national targets can be met.

CleanMax has helped 150+ largest corporates in India in their solar journey. It's one of the largest rooftop solar developers in Asia. Connect with us to know more about solar energy at Contact Us or write to [email protected].