Eligibility Criteria for Net Metering i.e. Upper cap and Lower cap | 1 kW–1 MW |
---|---|
Banking Norms for Rooftop | Yearly |
Key Approvals required for Rooftop | 1. CEIG approval 2. No net metering |
DISCOMs | |
Key Regulatory Charges/exemptions for Rooftop (if any) For more details visit individual DISCOM website. | Rooftop solar PV system under gross metering scheme / net metering scheme, whether self-owned or third party owned and installed on eligible consumer premises are exempt from payment of wheeling and cross subsidy surcharge. |
Eligibility Criteria for Net Metering i.e. Upper cap and Lower cap
1 kW–2 MW
Banking Norms for Rooftop
Yearly
Key Approvals required for Rooftop
DISCOMs
Key Regulatory Charges/exemptions for Rooftop (if any) For more details visit individual DISCOM website.
Rooftop solar PV system under gross metering scheme / net metering scheme, whether self-owned or third party owned and installed on eligible consumer premises are exempt from payment of wheeling and cross subsidy surcharge.
- feasibility of interconnection with grid
- available capacity of service line connection of consumer of premise
- the sanctioned load of consumer of the premise
Source: Centre for Energy Finance, Individual DISCOM websites
Disclaimer: The information presented above is for educational purposes only. All the data provided in the article above are approximate values derived from third party sources, research articles or on ground experience and CleanMax would take no responsibility or have any obligation over the correctness of data. The regulatory policies get updated from time to time and it is highly encouraged that you head over to individual DISCOM sites to refer the latest changes.
NOC | No Objection Certificate |
HERC | Haryana Electricity Regulatory Commission |
APPC | Average Power Purchase Cost |
CEIG | Chief Electrical Inspector to Government |
CDM | Clean Development Mechanism |